Issue #8

Fall 2004

The Basin Bulletin

Newsletter for Stakeholders of the Raritan Basin Watershed


Somerset County Wetland Mitigation Bank

Project Background

In 1998, Somerset County began planning an 8.1-acre wetland mitigation bank.  The project had three objectives:

1.      Serve as compensation for wetland impacts associated with past Somerset County infrastructure projects;

2.      Serve as a credit or bank for future infrastructure projects planned by Somerset County; and

3.      Be an amenity to the County Park System.

Mark Gallagher, Vice President of Princeton Hydro, LLC, developed the conceptual design for the project.  The formal engineering design was prepared under the direction of  Geoffrey Goll, PE, also of Princeton Hydro. Carl Andreassen, PE, the Principal Hydraulic Engineer for Somerset County, served as the County’s project manager. 

The goal of the mitigation project was to create a floodplain wetland system composed mostly of forested wetland that would provide several important wetland functions, including flood storage, sediment removal and wildlife.  The project site is located in an agricultural area of Branchburg Township, along the South Branch of the Raritan River.  The selected site was chosen due to its proximity to the South Branch and the presence of wetlands similar to those planned for the project downstream.  The naturally occurring wetland was used as a model for the mitigation bank.  

Somerset County is also working to develop this site as a County park with public access. 

Project Design

The primary objective of the wetland mitigation was to construct 8.1 acres of emergent and floodplain forested wetlands from an existing upland agricultural field, thereby creating wetland habitat and increasing the flood storage capacity of the floodplain. Extensive earthwork was required in order to achieve the desired goals.  The surface elevation was lowered and an existing backflow channel expanded to establish wetland hydrology.  By lowering the surface elevation, the retention of storm water and stream backflow during flood events was facilitated.  The retention of surface water in the mitigation site will increase the duration of inundation/saturation typical of a floodplain wetland.  The wetland was designed to flood at a frequency of four times a year.  The desired flood frequency and depth of flooding was determined through the use of  hydrologic modeling.  The model was also used to evaluate tractive force and flow velocity at different flood stages, depths and cross sections to guide the mitigation design.

In the early developmental stages of the project, the wetland vegetation will be an a patchwork of areas dominated by shrubs or trees, thus increasing the wetlands structural complexity and habitat value.  A system in which there are patches of trees and shrubs in a matrix of herbaceous plants will serve as recruitment for bird-disseminated seeds, leading to a plant community that will, over time, appear more similar to a natural wetland than a mitigation site. 

The proposed mitigation design will incorporate three distinct vegetation planting types.  Floodplain forested wetlands will provide the framework for the development of a riparian-forested wetland.  Scrub-shrub wetlands will increase the habitat complexity of the site by providing good cover and/or food for wildlife.  Emergent wetland plantings will help establish a diverse wetland habitat.  The species selected for the project were limited to indigenous species that are common components of the local riparian or floodplain flora.

Construction on the project began in the spring of 2003 and was completed in June of 2004.       

The project is located within a County park.  Therefore, a trail system was included, as part of the project design, and a small pedestrian bridge will provide access to the created wetlands and the South Branch for the public.  The County also entered into the Partners for Wildlife Program sponsored by the USFWS to control the invasive species reed canary grass (Phalaris arundinaceae) and to re-vegetate the treated areas with woody plants.  Trout Unlimited has also worked on stabilizing the bank of the segment of the South Branch that is on the property.  

Although, only a few months old the completed project is not only a naturally looking feature of that South Branch Raritan River floodplain but already supports a diverse wildlife community.

One of the important elements of this mitigation project was that it was designed to fit naturally into the site’s landscape and complement other existing natural communities.  The County’s willingness to participate in the USFWS’s Partners for Wildlife Program served to further enhance the wildlife value of the this portion of the South Branch.  The efforts of the USFWS in concert with the County’s mitigation project has created the foundation for the development of a diverse floodplain community. 

For more information on this project, contact:   Mark Gallagher, Princeton Hydro, LLC mgallagher@princetonhydro.com

Carl Andreassen, Somerset County Engineering Department andreassen@co.somerset.nj.us

Back to Basin Bulletin