Issue #14 

Winter 2006/2007

The Basin Bulletin

 

 Newsletter for Stakeholders of the Raritan River Basin

Prepared on behalf of the Raritan Basin Watershed Alliance

     


 

New Jersey Water Supply Authority

Hoffman Park Stream Restoration Project

Union Township, Hunterdon County, New Jersey

 

In 2003, the New Jersey Water Supply Authority (NJWSA) received a Targeted Watersheds Grant from the United States Environmental Protection Agency (EPA) to protect surface water quality in the Raritan River Basin. To identify implementation projects for this grant, the Authority conducted assessments of streams throughout the Spruce Run Reservoir watershed.  Three stream restoration projects were conducted as part of the grant:

·           Crystal Springs, Spruce Run (see Fall 2006 newsletter for more details);

·           Old Farm Road, Mulhockaway Creek; and

·           Hoffman Park, Mulhockaway Creek.

The Hoffman Park Stream Restoration Project is located on a branch of the Mulhockaway at the eastern end of the park, off Mechlins Corner Road.  Hunterdon County owns and manages the park.  Prior to implementation of the Authority’s project,  this reach of Mulhockaway Creek followed a relatively straight course through forested upland and wetland areas. A deteriorated and undersized culvert was present under the access road.  An accumulation of sediment had occurred on the upstream side of the culvert. Streambank erosion was evident upstream of the culvert and scour on the downstream side of the culvert resulted in an approximately five-foot drop in elevation from above the culvert to below.  The stream channel had incised approximately five feet below the top of the bank downstream of the culvert, leading to banks that were approximately six feet in height, eroding and unstable. 

Downstream face of culvert prior to construction

 

The Authority hired the Louis Berger Group, Inc. to design a stream restoration project that would replace the culvert, better connect the stream with its natural flood plain and riparian wetlands and reduce sediment movement to Spruce Run Reservoir.  We worked with a team of technical experts, including Hunterdon County Parks, the Delaware River Basin Commission and the Natural Resources Conservation Service to select a design that would best accomplish our goals.  The project is located within the Highlands Preservation Area;  we received the first Highlands permit issued for such a project in June 2006. 

 

The project design included the following:

·            Adjust stream pattern and profile:  The stream sinuosity, or pattern, was adjusted to establish a stream slope that can transport the sediment load without degrading or aggrading the channel. 

·            Adjust stream dimension:  A bankfull bench was established along the stream channel to provide a place for energy dissipation of water and sediment during high flow events.

·            Install instream structures to stabilize the stream:  Several types of in-stream structures – log vanes, cross vanes and root wads -  were installed to stabilize the stream bed, to reduce streambank erosion and reduce the energy of water during high flow events.

·            Replace the culvert system:  The culvert was replaced with a concrete bridge that spans the stream to provide fish passage and improve flow and sediment transport. 

·            Plant native vegetation:  An herbaceous seed mix and annual cover crop were planted at the end of construction in August and September.  More than 400 trees and shrubs and approximately 1,400 willow and dogwood stakes  were planted in November.

One interesting condition in our Highlands permit was the requirement to have a qualified herpetologist monitor the site during active construction.  What’s a herpetologist?  A biologist who specializes in reptiles and amphibians - frogs, toads, turtles salamanders, to name a few.  At Hoffman Park, the species of concern were bog turtle (endangered)  and wood turtle (threatened).  There is habitat for both species near the project, and both have been sighted in other areas of the park. 

Hunterdon County Parks provided qualified herpetologists who did 2 “turtle trainings” for Authority staff and staff from Vollers and Berger.  In addition, County Parks staff were on-site every day during active construction.  While we didn’t find any turtles during construction,  we did move many, many frogs and salamanders out of the construction zone  – most of them more than once!

Construction began at the end of June 2006.  Vollers Excavating & Construction of North Branch, NJ served as the project contractor and Berger provided full-time construction management. 

  In order to complete the work, the stream was diverted around the project reach, through an adjacent borrow pit and back into the channel at the downstream end of the project reach.  This enabled Vollers to work in dry conditions as they carved the new channel and bankfull bench and installed the structures.

 

Construction Mobilization, June 2006

 

On September 14th, the big day arrived – time to re-divert the stream back into its new channel.  As the berm between the new channel and the diversion channel was removed, the “stream paparazzi” followed the movement of water through the new channel, over and around the in-stream structures, through the new bridge and to the end of the project reach. 

 

New arch concrete bridge, September 2006

The project area experienced several significant storms following completion of construction – one on the day after we re-diverted the stream.  These storms gave us an indication of just how dynamic the Mulhockaway stream system is and reminded us that the computer models that help us design such projects can’t predict everything.  Stream systems are not static – we expect them to change over time, but our project reach experienced many changes very quickly, leading to the need for adaptive management.  Authority staff have been working with Berger to design modifications to three of the structures that were installed.  The Authority’s Grounds Maintenance staff installed the modifications in December 2006.  

Installation of cross vane

The Authority is monitoring the success of the project in several ways.  First, we’ll be continuing our macroinvertebrate monitoring at Hoffman Park and our other two restoration sites.  Macroinvertebrates are the little organisms that live in the substrate of the stream – worms, mayflies, stoneflies and others. We have several sets of pre-construction samples to use as comparison.  This will enable us to see how quickly the stream is recolonized by macroinvertebrates and if the project affected the diversity of species present.   We’ll also be monitoring the success of the vegetation that was planted. 

Visitors to Hoffman Park Site

 

The third type of monitoring is of what are called geomorphological characteristics.  By surveying the locations of the stream bed, the banks, the meanders of the stream, we can tell how the stream is moving within its new pattern and determine if it is stable.  We expect the stream to move within a certain range of these characteristics.

 

Watershed staff spent much of the summer at the project site, observing the construction, monitoring for turtles and giving tours to a variety of guests.  These included representatives of the D&R Canal Commission, NJDEP Commissioner Lisa Jackson and several of our board members.  Many Authority staff visited the project throughout construction.  If you haven’t been out to the project yet, or would like to see how the stream is progressing, please contact Kathy Hale in the Watershed Unit (908) 685-0315, x28 or khale@raritanbasin.org for a tour.

Completed cross vane

Installation of log vane

Completed Project, October 2006